Consolidated Construction Consortium Ltd. v. the Tamil Nadu Water Supply and Drainage Board(Twad)
Case brief
What is this about?
The Madurai Bench allowed the writ petition partly, directing the TWAD Board to release Rs. 3.80 crores to the petitioner contractor immediately. The Board can retain the balance pending confirmation that the Municipal Administration sanctions the Capital Grant Fund within three months, after which the Board may release the retained sum as per the contract terms.
What did the court decide?
Directing the TWAD Board to release Rs. 3.80 crores to the petitioner immediately and to release the remaining balance after the Municipal Administration sanctions the Capital Grant Fund within three