(4)When the matter was listed on 03.12.2019, this Court directed printing the name of Mr.S.Thiruvengadam, learned Standing counsel fort the 6th respondent and when the matter is listed today, the 7th respondent has filed a counter affidavit and would state among other things, that the 8th respondent had divided a plot and approached the Executive Engineer, PWD, WRO, Arani River Basin Division, Chepauk, Chennai, and the District Collector with a request to form a bridge upon Otterinullah and offered to give a land with 5 feet width and 317 metres in length and it was also agreed and Tmt.Gnana Achariyammal and 7 others [including the 8th respondent herein] had also executed a Gift Deed, gifting an extent of 1585 sq.ft., of land in favour of His Excellency the Governor of Tamil Nadu, for construction of the said bridge and that apart, also remitted a sum of Rs.25,85,000/- in favour of the Executive Engineer, PWD, WRO, Arani River Basin Division, Chepauk, Chennai, towards the cost of the construction of the said bridge. Subsequently, permission was cancelled by the District Collector and it was revoked with a condition that an undertaking shall be obtained from the 8th respondent for user of the said bridge for public pathway also and it was also agreed and as such, the pathway came into being. The learned Standing counsel further took a stand that the amount of construction of the bridge was paid by the 8th respondent to the District Collector, who in turn, deposited the same to the credit of PWD and the plans and estimates were prepared by PWD in terms of paragraph 207 of the Tamil Nadu Public Works Department Rules, considering the hydraulic parameters of the Otteri Nullah and the bridge was constructed long back, especially, taking into consideration,