“6. I further submit that the electricity is given to one J. Ruben at Door No.5, Cantonment on 02.07.1996, on the basis of his application dated 04.05.1996 submitted along with the NOC from Cantonment Executive Officer, St. Thomas Mount, Pallavaram and while so the amended provisions of Clause 27 (12) was not in force and the Clause 27(12) of the said code come into force only on 21.6.2006 and the service connection to Mr. Chinnayogaiyya at Door No.20, Cantonment is also effected on 27.12.2000 (i.e.) which is also prior to the amendment made to Clause 27 (12). 7. I further submit that with regard to Mr. P. Konddaiya at Door No.18, Cantonment the electricity supply is effect on 03.08.2011 without knowing the amendment in Clause 27(12) of the T.N. Electricity is effected and thereafter from 03.08.2011, there was no such electricity supply effected till date as the Cantonment Tahsil instructing the TANGEDCO that no such electricity supply shall be effected without the production of the No objection certificate (NOC) from the Cantonment Tahsildar, as this lands are Government Promboke land and falls within the territory of the cantonment and defence area and hence the electricity service request was not considered due to the regular follow up from the Cantonment Tahsildar and also under the circumstances that none of the writ petitioners had produced the NOC from the Cantonment Tahsildar as contemplated under Clause 27(12) of the said code and hence the Writ Petitioners are not entitled to get the electricity supply to their recent huts occupation without the production of NOC from the said Cantonment Tahsildar being a mandatory requirement under the said code.”