The Government of Tamilnadu v. a.Rangasamy
Case brief
What is this about?
A road contractor's award for overhead charges and loss of profits was set aside as time-barred. Later final-bill payments did not extend limitation for that separate damages claim. The court upheld the severable award of interest on delayed payments and partly allowed the challenge.
What did the court decide?
Award for loss of overhead charges and erosion of profit set aside; award of interest on delayed payments upheld.