M/S.Sun Facilities Service v. the Divisional Railway Manager
Case brief
What is this about?
The Court heard two original applications seeking interim injunctions against railway contract terminations on arbitration grounds. While granting relief to the first applicant, the Court dismissed the second application due to the applicant's failure to furnish the required Performance Bank Guarantee, making the existing injunction absolute.
What did the court decide?
O.A.No.702 of 2018 dismissed; interim injunction in O.A.No.395 of 2018 made absolute; parties directed to commence arbitration.