E.Peter Rubans v. the Chairman
Case brief
What is this about?
Single-judge bench condoned a delay of 160 days in filing a writ appeal against an order in W.P.No.25862 of 2018, treating the appeal as within time and assigning it a regular number.
What did the court decide?
Delay of 160 days in filing the writ appeal was condoned; appeal treated as within time and allocated regular number.
What the court decided
C.M.P.No.1332 of 2020 in W.A.No. SR 7490 of 2020
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 10.07.2020
CORAM :
THE HON'BLE MR.A.P.SAHI, CHIEF JUSTICE
AND
THE HON'BLE MR.JUSTICE SENTHILKUMAR RAMAMOORTHY
C.M.P.No.1332 of 2020
and W.A.No. SR 7490 of 2020
E.PETER RUBANS .. Petitioner
Vs
- 1 THE CHAIRMAN MANAGING DIRECTOR TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION LTD.
- NO.144 ANNA SALAI, CHENNAI.
- 2 THE CHIEF ENGINEER/PERSONNEL TAMIL NADU ELECTRICITY GENERATION AND DISTRIBUTION CORPORATION LTD.
- NO.144 ANNA SALAI, TNEB, CHENNAI.
Issues for consideration
1 issue framed by the court
Whether sufficient cause was shown for condoning the delay of 160 days in filing the writ appeal.
Parties & counsel
- petitioner
E.PETER RUBANS
- respondent
THE CHAIRMAN MANAGING DIRECTOR TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION LTD.
- respondent
THE CHIEF ENGINEER/PERSONNEL TAMIL NADU ELECTRICITY GENERATION AND DISTRIBUTION CORPORATION LTD.
- respondent
THE SUPERINTENDING ENGINEER TAMIL NADU ELECTRICITY GENERATION AND DISTRIBUTION CORPORATION LTD.
Coram
Case details
As recorded by the court registry
Similar cases