The petitioner was awarded with a contract for providing Clean Water Supply Scheme to 254 rural habitations in Vadamadurai and Vedasandur Unions. As per the agreement, the petitioner has to complete the work within a period of 12 months. But, after issuing the work order, the respondents are not able to get approval from the National Highways, State Highways and Railway department for laying pipeline. Hence, the respondents divided the above scheme into three segments of 51, 96, 107 habitations. So far as 51 habitation is concerned, the petitioner has completed the scheme within the prescribed period. In so far as other remaining two segments are concerned, the petitioner was not able to complete the same, since the respondents did not get permission from the highways authorities as well as railway department. In the above circumstances, the respondents has also extended the time limit for segments 1 and 2. In the meantime, the petitioner has provided a water connection to 96 habitations, and the work in respect of another 57 habitation was also completed. So far as third segment is concerned, the petitioner has completed nearly 25 habitations, but that was not inspected and measured by the respondents. Only because of the delay in getting permission from the highways authority by the respondents, the petitioner could not proceed with the work, for which, the petitioner cannot be blamed.