the application submitted by the plaintiff. The only dispute is that whether the service connection was effected to the bore well or to the open well. In this case, the application submitted by the plaintiff before the Tamilnadu Electricity Board was marked as Ex.B1. In the said application, it was mentioned by the plaintiff that the service connection was required to the well situated to the extent of 14 feet into 12 feet. Alongwith the above numbers, the other numbers pertaining to the extent of land in other Survey number was mentioned. The said numbers are surveyed on 01.04.1993 by the Village Administrative Officer. So also according to the certificate issued by the Village Administrative Officer, there was a well to the extent of 14 feet into 12 feet situated in S.F.491.4. During the time of trial, the Village Administrative Officer, Alavaipatti has been examined as DW2. DW2 has categorically stated in his evidence that on 23.03.1997, the plaintiff Sundaram, requested him to issue a certificate to his land and upon his request, he issued a certificate alongwith Topo Sketch. The certificate issued by the Village Administration Officer was marked as Ex.B5 and the Topo Sketch was marked as Ex.B6. He specifically stated in his evidence that in S.No.491/4 there was a well and the same was belonging to the plaintiff. Further, as per Exs.B5 & Ex.B6, the Village Administration Officer, confirmed the same. The contents of Exs.B5 & 6, confirmed the above said evidence. According to DW2 and Exs.B5 and 6, a well was situated inside the field of the plaintiff. In the evidence given by DW1, DW3, who were the Junior Engineers of the Tamilnadu Electricity Board, it is seen that before effecting service connection, the land in which, the well was situated was inspected and only thereafter, the service connection was effected. So also the witnesses examined on the side of the defendants were also deposed evidence in favour of the plaintiff. The Officer, who effected the service connection to the plaintiff's land himself admitted that at the time of effecting the service connection there was a well in the field, which was belonging to the plaintiff.