Claim Description of Claim Amount
No. claimed (Rs.)
1. Idling of labour and machiner awaiting to 2,37,40,000/-
start the work from 01.12.2007 to
07.04.2009 (493 days) that is till the
foreclosure of the work
2. The materials were purchased for the 17,17,750/-
work and could not be utilized due to not
allowing the work to be executed and
some lost in wear and tear and theft and
balance resold in market at 50% of cost
of materials is claimed
3. Claim for expenditure incurred on test 60,000/-
reports which were not finalized
(approx.)
4. Loss of expenditure incurred on 2,00,000/-
establishment of office building, godown
for materials, sheds and mess charges
5. Loss o profit at 10% of the agreement 29,25,130/-
value for not allowing the work to be
executed.
6. Damages claimed on the expenditure Not quantified
incurred on claim Nos.1, 2, 3 & 4 at
15% p.a. till the date of their payment