Construction on 23.09.2016 registered as Doc.No.15723 of 2016 with the respondent Company to purchase an apartment in No.M-649 in the 6th Floor, Block No.M, Phase III of the Resdential Project, TEMPLE WAVES with super built up area of 645 sq.ft (including proportionate undivided share in the common constructed area). The sale consideration was fixed at Rs.26,32,113/inclusive of all amenities. The Sale Deed has been executed in favour of the petitioner vide Doc.No.15724 of 2016 dated 24.10.2016. But the respondent failed to keep up the promise as per the agreement even though the petitioner has complied with all the formalities and payments as per the schedule. As per the construction agreement, the respondent had agreed to complete the construction and hand over the apartment on or before March 2017, but when the petitioner visited the site, no work has been completed. Hence, the petitioner had sent Arbitration Notice dated 10.05.2019 to the respondent, but no proper response was shown on the side of the respondent. Hence, the petitioner has filed this petition.