to the petitioner by the claimant. This fact is not in dispute. Total contract price was a sum of Rs.3,81,60,000/- i.e., Rs.1,80,000/- per car space. As per the Agreement the site had to be handed over the Petitioner on or before 3.10.2007. However, the site was given to the Petitioner only in June 2009. The parties have in fact consciously agreed for extension of further time. Thereafter, they have also entered into a tripartite agreement on 30.09.2010 between the Claimant, Respondent and Kacon India Limited to complete the project before 15.10.2010. The learned Arbitrator has factually found that even after the tripartite agreement, the petitioner did not complete the project. Contrary, the petitioner diverted the materials purchased for the claimant's project, to their other projects. Learned Arbitrator also found that stoppage of materials by M/s. Kacon India Ltd was solely due to the respondent's attitude and not fulfilling its obligation to the sub-contractor as regards the payment.