Indian Oil Corporation Ltd, Ap State Office, v. M/S. N.R.P Projects Private Ltd., Rep.by Its Partner Mr.Hitesh J.Patel
Case brief
What is this about?
The Court disposed of a petition and application to set aside and stay an arbitration award. Finding no merit in setting aside the award under Section 34 but noting prolonged delay and high interest liability, the Court directed a partial refund of deposited money to the applicant as interest compensation before releasing the balance to the respondent.
What did the court decide?
The applicant was allowed to recover Rs. 75 lakhs from the deposited funds as interest for the period 2009-2017; the balance amount was directed to be paid to the respondent.