Ishvaryam Windmills Private Limited v. M/S. Nordex India Pvt. Ltd. and Another
Case brief
What is this about?
This application challenged an existing interim injunction restraining a respondent from invoking Step-in rights under a commercial agreement. The court held that while delays necessitated the Step-in right under the contract, the existence of such a contractual right precluded the injunction. The original order was vacated, and the matter directed to arbitration.
What did the court decide?
Interim order of injunction dated 24.07.2019 stands vacated, Application dismissed.