B. Sathyamoorthy, v. the Executive Engineer
Case brief
What is this about?
The Madras High Court quashed a working sheet imposing penalties for alleged electricity theft. The court held that the finding of theft was arbitrary as the department failed to specify tariff limits for commercial usage, making the assessment erroneous and unjustifiable.
What did the court decide?
The impugned working sheet was quashed and remanded for reconsideration; consequential provisional and final assessment orders set aside.