Ballarpur Industries Limited v. Karapara Project Engineering
Case brief
What is this about?
Petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an award in a boiler erection and commissioning dispute. Allegations that the arbitrator exceeded the terms of reference, that the claimant approbated and reprobated, and that the award was unscientific were rejected; the findings were held to be findings of fact, not perverse. Petition dismissed.