P.Murugan, v. The District Collector
Case brief
What is this about?
In a writ petition under Article 226, the Court directed the Tahsildar (Second Respondent) to implement the recovery order of the District Collector (First Respondent) regarding a Labour Court award, to be completed within three months.
What did the court decide?
The Second Respondent was directed to implement the First Respondent's order dated 06.01.2014 regarding Labour Court award recovery within three months.