N.Thangaraju, v. The Chief Manager
Case brief
What is this about?
The court directed the District Collector (4th Respondent) to determine compensation for land utilized for power installation and right of way, referencing Government of India guidelines. It vacated a prior status quo order and fixed eight weeks for the Collector to decide on merits after the petitioner files the claim. Non-compliance mandates appearance before the court.
What did the court decide?
The District Collector is directed to consider the compensation application for land used for power installation and right of way and pass an order on merits within eight weeks.