M/S.Mugilan Enterprises v. the Chief Engineer
Case brief
What is this about?
The court dismissed a contract suit filed by a civil contractor against government engineers. The contractor claimed termination of the contract due to forest and local obstructions. The court found the plaintiff failed to execute work, refused official notices, lacked evidence for delays or losses, and the suit was struck down for non-joinder of the State Government.
What did the court decide?
The suit was dismissed with costs on the grounds of non-joinder of necessary parties and lack of evidence regarding breach.