The Superintending Enginner v. P Samiappa Gounder
Case brief
What is this about?
This appeal suit challenges a money decree in a construction contract dispute. The High Court dismissed the appeal, holding the suit was within limitation due to Section 80 notice service. The court found the plaintiff entitled to recovery based on admitted contract terms and the defendant failed to specifically deny the existence of the agreement.
What did the court decide?
Appeal suit dismissed with costs. Judgment and decree of the trial Court in O.S. No.137 of 2005 are confirmed.