This writ petition has been filed by the petitioner challenging the award passed in O.P. No. MSEFC/CR/34/2014, dated 10.10 . 2014 by which the petitioner was asked to pay a sum of Rs.2,85,456,823/- with compounding interest. The second respondent company incorporated under the Companies Act, 1956, which is engaged in the business of executing works contract in the field of supply of piping, fittings, valves and appurtenances. The petitioner has placed two purchase orders dated 15.09.2011 & 12.11.2011, for supply of piping and appurtenances for the captive power plant project with the second respondent. Though 95% of the materials were supplied by the second respondent, the petitioner has not made the required payment. Thus, the second respondent preferred a case against the petitioner, before the first respondent Council.