What is this about?
Petitioner seeking shift of electricity connection to new bore well on ground of existing well drying up. Court held patta objection by third party not ground for denial if petitioner's patta stands valid. Directed shift within four weeks.
What did the court decide?
First respondent directed to shift EB service connection from common well to petitioner's bore well in four weeks upon payment of charges.