T.Gireeshan v. State of Kerala
Case brief
What is this about?
T. Gireeshan v. State of Kerala & Others, WP(C) No. 5268 of 2017, High Court of Kerala (Ernakulam), decided 08.04.2025 by Mohammed Nias C.P., J. Land acquisition compensation enforcement: writ allowed directing State/PWD respondents to comply with Ext.P4 decree in O.S.No.72/2013 (Munsiff Court, Ernakulam, ex parte decree dated 12.4.2016 declaring ownership and entitlement to compensation for property acquired for Statute Junction expansion, Tripunithura); three months plus two months timeline; respondents' application to set aside ex parte decree noted; petitioner's review dismissed; no statute or precedent cited; no quantum fixed.
What did the court decide?
Direction to the respondents to comply with the Ext.P4 decree of the Munsiff Court, Ernakulam: three months to take such steps, and payment of the compensation directed therein within a further period of two months.