M/S. Sreenarayana Constructions Pct.Ltd v. State of Kerala
Case brief
What is this about?
The Court disposed of a writ petition challenging termination of a construction award. It directed the Additional Respondent to consider the petitioner's representation after an opportunity of hearing, complete measurement of work carried out, and examine the contention regarding absolution from the risk and cost clause due to project abandonment, to be done within four months.
What did the court decide?
The Additional 7th Respondent is directed to consider Ext.P20, hear the petitioner, complete measurement of work done, and decide on absolution from risk/cost dues within four months.