Roy Mathew. C, v. Kerala Water Authority
Case brief
What is this about?
A contractor sought release of a withheld amount of Rs.25,43,599/- under a part bill for construction work completed to 97% for the Kerala Water Authority. The respondents raised no objection; the court directed disbursal within two months.
What did the court decide?
Direction to respondents to disburse the withheld amount of Rs.25,43,599/- within two months.