Sukesini Constructions and Developers (India) Pvt. Ltd. v. State of Kerala
Case brief
What is this about?
The High Court allowed the writ petition seeking to quash an order denying payment for completed construction works. Relying on a prior judgment, the Court directed the Chief Engineer to constitute a committee to audit the works and decide the payable amounts, with disbursement mandated within two months of the audit completion.
What did the court decide?
Constitution of a Committee to audit works and determine payable amounts; order to be completed within four months, with disbursement within two months thereafter.