T.Asokan v. State of Kerala
Case brief
What is this about?
PWD contractor sought quashing of a Government order rejecting his claim for revision of contract rates for a bridge construction completed under adverse site conditions. The court set aside the rejection order, noting the Chief Engineer's recommendation was not considered, and directed fresh assessment with hearing within three months.
What did the court decide?
Ext.P20 quashed; Government directed to re-assess and pass appropriate orders after hearing petitioner, within three months.