Eldhose v. the Elappara Grama Panchayath
Case brief
What is this about?
A contractor challenged Panchayat demand notices seeking alleged excess payments received for renovation work, along with Revenue Recovery notices. As the notices were issued without hearing him, the court set them aside, directed the Director of Panchayat to reconsider after a hearing within four months, and left the limitation question open.
What did the court decide?
Ext.P1, P2, P5 and P6 set aside; fresh reconsideration with opportunity of hearing ordered within four months.