The Unit Chief v. M/S. Sapthazeal Private Limited
Case brief
What is this about?
Principal employer challenged a Regional Labour Commissioner order directing it to pay minimum-wage arrears of its contractor's housekeeping workers. The court held the Commissioner lacked jurisdiction to adjudicate during conciliation and that housekeeping contracts fall outside the Contract Labour Act's 'contractor' definition; the order was quashed.
What did the court decide?
Ext.P4 order quashed; declared petitioner not liable for workers' wages; liberty preserved to unions to pursue claims against contractor.