George Mathew v. Kerala Land Development Corporation Limited
Case brief
What is this about?
The petitioner, a contractor, filed a writ petition seeking payment for delay in disbursing a bill worth approx. Rs. 31.68 lakhs. The court directed the respondents to complete payment within six weeks.
What did the court decide?
Directing respondent 1 and 2 to disburse the amount due to the petitioner under Exhibit P1 work bill within six weeks.