Abdul Kalam v. Power Grid Corporation of India Ltd.
Case brief
What is this about?
Revision petition against compensation awarded for trees cut and land value diminution caused by drawing 400 KV transmission lines across the petitioner's land. The High Court found the assessment deviated from expert evidence and used an incorrect multiplier, set aside the order, and remanded for fresh determination.
What did the court decide?
Impugned order set aside; original petition remanded to court below for fresh consideration and fixation of just compensation within four months.