Viskons Projects, v. Delhi Metro Rail Corporation
Case brief
What is this about?
This writ petition challenges the Delhi Metro Rail Corporation's refusal to release the petitioner's performance security (Bank Guarantee) after the Defect Liability Period expired. The Court rejected the respondent's arguments regarding maintainability and arbitration pendency, holding that the action was arbitrary and directed the release of the guarantee within ten days.
What did the court decide?
The writ petition is allowed. The respondents are directed to release the Bank Guarantee of Rs.50,00,375/- within ten days of receipt of a copy of this judgment.