What is this about?
Four writ petitions challenging the cancellation of Akshaya Centre licenses. The High Court observed that the impugned orders were passed without hearing the petitioners. It allowed the petitions, directing the Director to reconsider the file de novo, including pleas regarding employment relinquishment, health improvement, or transfer to third parties, within one month while maintaining status quo
What did the court decide?
Allowed W.P. Nos. 4507/2023 and 12111/2023; allowed W.P. Nos. 3142/2023 and 4354/2023 with directions to Director to reconsider matters including health and transfer pleas within one month.