Perfect Engineers and Contractors, v. State of Kerala
Case brief
What is this about?
The High Court of Kerala, in a writ petition, set aside PWD orders rejecting the petitioner's claim for construction incentives. The Court held that since the petitioner's work was completed before circulars extending the application deadline were issued, they were not guilty of the procedural time-bar. A direction for reconsideration was granted.
What did the court decide?
Set aside Exts.P11 and P12; directed competent Authority to reconsider claim under P9/P10 Circulars within three months; directed disbursement of eligible incentive within two months thereafter.