Graceland Foundation v. Kerala Real Estate Regulatory Authority
Case brief
What is this about?
The High Court examined the applicability of RERA to a project where the promoter claimed deemed occupancy before the Act's commencement. It held that the completion certificate produced was not as defined under Section 2(q) of RERA, and that occupancy certificates were issued after 01.05.2017, making registration mandatory.
What did the court decide?
Promoter directed to apply for registration within 30 days; on failure, penalty of Rs.10,00,000/- as directed by the Real Estate Regulatory Authority shall be paid.