T.v.Sunil v. the Kerala Agro- Industries Corporation Ltd.
Case brief
What is this about?
In a contract dispute over construction works, the Court directed the District Animal Husbandry Office to pay the first respondent the final bill amount, enabling the first respondent to disburse the admitted sum of Rs.13,68,440/- to the petitioner within two weeks.
What did the court decide?
Third respondent to pay Rs.20,88,246/- to first respondent; first respondent to pay Rs.13,68,440/- to petitioner within two weeks each.