K P Shajan v. Thrissur Corporation
Case brief
What is this about?
Petitioner sought writ to direct public authorities to pay unpaid construction bills totaling 47.26 lakh. Court held diligence of work is established but due to pending vigilance inquiry, payment was delayed. Directed respondents to process and pay bills within two months after petitioner furnishes an indemnity bond.
What did the court decide?
Respondents directed to process and pay the petitioner's bills within two months after obtaining an indemnity bond from the petitioner.