Zubair v. Vs State of Kerala
Case brief
What is this about?
Petitioner challenged inordinate delay in releasing security deposit and retention amount for water pumping main work completed in 2020. Court held delay due to non-commissioning caused by other contractors is unreasonable and directed respondents to release dues within four months upon executing a bond.
What did the court decide?
Respondents directed to release amount due within four months from the date of executing a simple bond by the petitioner.