Rs Development and Constructions (I) Private Limited, v. State of Kerala
Case brief
What is this about?
Petitioner company sought stay on contract work due to price escalation. Court declined to decide merits immediately, citing contract mechanism. Directed parties to resolve dispute via representation process with respondent boards within three weeks.
What did the court decide?
Petition disposed permitting petitioner to submit representation to 4th respondent for redressal of grievance; 4th respondent to take decision within three weeks after hearing.