Ranjith Chandran v. Kerala State Electricity Board Limited
Case brief
What is this about?
Separate electricity supply to two villas and energisation of a shared transformer were disputed. The court directed processing of the two villas’ independent connection application within two months, subject to conditions, and immediate energisation of the existing transformer for the other villas. All three petitions were disposed of.
What did the court decide?
Process the independent connection application for villas 6 and 8 within two months of receipt of the judgment; immediately energise the existing transformer for the other villas.