Shamsudheen A.I v. the Superintending Engineer
Case brief
What is this about?
Petitioner sought mandamus for expedited completion of a bridge reconstruction project and provision of a temporary service road. The Court examined the delays caused by floods, lockdowns, and cyclones, noting partial progress and an interim footover bridge, ultimately disposing the petition.
What did the court decide?
Directed respondent No.5 (contractor) to complete the bridge work as agreed and make it motorable to the public.