Nizarudeen v. National Highways Authority of India
Case brief
What is this about?
The Court addressed two writ petitions regarding land acquisition for a National Highway. It directed the Compensation Authority to disburse eligible compensation to the property owner after verifying title documents within one month. The Project Director was directed to verify the tenant's claim and decide on demolition continuity based on whether the area is included in the acquisition Award.
What did the court decide?
The CALA is directed to disburse compensation to the petitioner within one month. The Project Director must verify if the claimed area is in the Award and order demolition or allow continuation accord