A.D.John v. the State Environmental Impact Assessment Authority - Seiaa
Case brief
What is this about?
Writ petition by a granite quarry owner seeking direction to the 1st respondent to decide his extension application. Court directed the respondent to take a final decision within two months, noting the need to consider a central ministry notification.
What did the court decide?
Directed the 1st respondent to take a final decision on the application for extension of Environmental Clearance within a period of two months.