Zerone Consulting Pvt. Ltd. v. K.S.E.B
Case brief
What is this about?
The High Court found errors in the calculation of connected load in the appellate authority's order regarding a disputed electricity tariff. The court set aside the order directing a fresh hearing on tariff applicability and connected load, and deferred coercive steps.
What did the court decide?
Ext.P13 order set aside; directions to Deputy Chief Engineer to decide appeal afresh within two months on tariff and connected load; coercive steps deferred.