Roopam Engineers and Contractors Private Limited v. Indian Space Research Organization (Isro)
Case brief
What is this about?
The High Court directed the respondent to reconsider the petitioner's claim for price escalation compensation under Clause 10C(ii) of a construction contract. The court held that arbitrary extension of bid validity and subsequent suspension prevented the 12-month completion norm from being applied to deny compensation for material cost hikes.
What did the court decide?
Ext. P17 and P19 set aside; 2nd respondent directed to reconsider representations and award compensation for escalation after adhering to judgment observations.