U.B.Ummrabba, v. the Project Director
Case brief
What is this about?
Directed the 2nd respondent to dispose of petitioners application under Section 3G(5) of the National Highways Act within three months, affording hearing opportunity to the petitioner and the NHAI competent authority.
What did the court decide?
Direction to dispose of Ext.P3 application under Section 3G(5) NH Act within three months, hearing petitioner and NHAI.