Southern Railway v. Cherian Varkey Construction Co. Pvt. Ltd.
Case brief
What is this about?
This appeal challenges a lower court order setting aside an arbitral award that rejected a contractor's claim as time-barred. The High Court held the claim was within the limitation period because the cause of action arose when the final bill was drawn without considering the contractor's claim, not when the work was completed.
What did the court decide?
The appeal was dismissed; the order dated 22.02.2020 in A.O.P No. 1247 of 2015 was affirmed.