Green Method Engineering (P) Ltd., v. the State of Kerala
Case brief
What is this about?
Petitioner sought recovery of dues. Court directed State to release recognized balance to contractor. Contractor to pay adjusted dues to petitioner after complying formalities. Other contentions left open.
What did the court decide?
Directed 3rd respondent to pay Rs. 8,31,322/- to 4th respondent. Directed 4th respondent to pay Rs. 12,74,730/- to petitioner after formalities. Other contentions left open.