S.Ambrose and Company, v. the General Manager
Case brief
What is this about?
The petitioner, a railway contractor, filed a writ petition seeking payment of the pending second part bill amount. The court directed the respondents to pay the due amount within two months from the date of receiving the judgment copy after confirming the debt.
What did the court decide?
Direction to the respondents to make the payment due to the petitioner within a period of 2 months from the date of receipt of a copy of this judgment.