Anzarudeen v. the Chief Executive Officer
Case brief
What is this about?
The High Court dismissed the writ petition which sought quashing of an order directing demolition of a check dam. The court observed that the petitioner had not obtained necessary permission and freed the petitioner to approach the relevant department with a fresh application within two months, maintaining the status quo.
What did the court decide?
The petitioner was directed to approach the 2nd respondent with a fresh application within two months; status quo till then.