Shaji.N.R v. the Kochi Corporation
Case brief
What is this about?
This writ petition by a civil contractor sought directions to the Kochi Corporation to process payment for completed beautification work. The Court directed the petitioner to cure specific minor defects regarding tiles and concrete work but ruled weep holes were not required. The petitioner was ordered to complete corrections within two weeks, and the respondents were directed to release 50% of th
What did the court decide?
Petitioner to cure defects in two weeks; Respondents to release 50% of dues in three weeks and balance by 31.03.2021.